CMGC / Design Build

City of Newberg – Wastewater Treatment Plant Repair, Restoration and Expansion

The work at the Newberg WWTP SP 202 involves two main sites, the IPS and Headworks. The work at the existing pump station includes the installation of (2) 84″ manholes, and approximately 180 lf of 36″ PVC sewer pipe, 28′ deep. Because of the depth, the close proximity to wetlands and the water table, the […]

City of Salem – Downtown Interceptor

Assist design engineer and owner in completion of project design. Services included material and subcontractor procurement, permitting, budgeting and developing the GMP. Construction involved installation of 4,000 LF of 48” RCP sanitary sewer 16-25 feet deep, construction of a 25’ x 40’ sewer consolidation structure, surface restoration, and traffic control in a highly visible and […]