Public Infrastructure Improvements

Clean Water Services – Onion Flat Trunk Sewer Upgrade

Emery & Sons was responsible for the installation of 298 linear feet of 42-inch sanitary sewer pipe, 4749 linear feet of 27-inch sanitary sewer pipe, 112 linear feet of 30-inch sanitary sewer pipe, 14 linear feet of 8-inch sanitary sewer pipe, 15 manholes, 236 linear feet of trenchless crossing and casing under Highway 99, dewatering […]

City of Portland – Piedmont Sewer Rehabilitation Projedt

The Piedmont Sewer Rehabilitation Project involves the new construction, replacement, and rehabilitation of combination sewer, sanitary sewer, and manholes in North Portland near N Lombard St. Work shall include, but not limited to: Construct, maintain, and remove temporary work zone traffic control measures. Construct, maintain, and remove erosion control measures. Construct, maintain, and remove temporary […]

City of Portland – 2016 Local Improvement Districts Project

The 2016 Local Improvement Districts Project involves the construction of street improvements along the following streets: NE Couch Ct: NE 3rd Ave – NE Couch St LID SW 45th Ave and California St LID Work shall include, but not be limited to: Perform all removal of structures and obstructions, clearing and grubbing, and earthwork operations. […]

City of Grants Pass – Webster Lift Station

Emery & Sons was responsible for the Construction of the Webster Lift Station No. 1, including below-grade wet well and valve vault, inlet gravity sanitary sewer pipeline, and above-grade control panel, backflow preventer, and associated site work. The Work also consists of decommission and partial demolition of the existing Webster Lift Station No. 1, pavement […]

City of Newberg – Villa Road Improvements Project

Emery & Sons was responsible for the installation of 272 linear feet of large diameter plate arch culvert, relocation and installation of 330 linear feet of 8 inch sanitary sewer and manholes, relocation of existing 8 inch ductile iron waterline, relocation of existing storm piping, construction of (4) headwalls, Ultra Block retaining wall system, fish […]

City of McMinnville – Cook School Sanitary Sewer Rehabilitation

Emery & Sons was responsible for the construction of approximately 9,382 linear feet of sanitary sewer mainline ranging from 6 to 18 inches in diameter and installation of approximately 1,675 linear feet of new storm sewer ranging 10 to 15 inches in diameter. Construction methods utilized for the improvements will include open trench excavation (4”-2,650 […]

City of Lake Oswego – Hydro Dam Lower Penstock Segment Replacement

Emery & Sons was responsible for the following: Removal and salvage of the existing 48-inch diameter wood stave pipe. Installation of 48-inch diameter steel and HDPE pipe. Connection to existing 48-inch steel pipe. Retaining wall construction Connection to existing concrete surge tower Installation of 60-inch diameter steel pipe under State St Bridge at McVey Ave. […]

City of Lake Oswego – Finished Water Pipeline – Schedule 3B

Work on this project consisted of the following: Construct approximately 12,877 LF of 48-inch diameter and approximately 749 LF of 42-inch diameter welded steel Finished Water Pipe (FWP), including valves, fittings and appurtenances. Construct approximately 212 LF of 18-inch diameter ductile iron potable water pipeline, including valves, fittings, and appurtenances (connection to existing pump station). […]